SWCC Shuqaiq Phase 2 — Piping & Pump Station Mechanical Works
Location: Shuqaiq, Saudi ArabiaPeriod: Under Mipe Co.Client: Saline Water Conversion Corporation (SWCC)Role: Krishna Uppala — Site Manager
Scope
Piping and spool fabrication, pump-station mechanical works, compressor room and valve station installation, spool/pantaloon fabrication at a purpose-built site workshop.
Technical Details
- Total piping scope: 400,000 dia-inch
- 2,000 m² spool shop built and equipped for the project
- Reported at 96% scope completion within a two-year programme
- Full pump-station mechanical installation and SS spool/skid works




This project represents prior professional experience of members of STECOO's engineering and leadership team before the incorporation of STECOO Steeltech Engineering & Construction Operations LLP on 29 June 2023.